Dynamics of construction as of 2021/08/01
01/08/21

Dynamics of construction as of 2021/08/01

Dear customers, we provide the dynamics of construction as of 01.08 for your attention .


• On tower "A", brickwork of the walls of the 10th floor is being carried out. Installation of aluminum window structures of 3-9 floors is in progress.

• On tower "B", brickwork of the inner walls continues.

• On tower "V", arrangement of internal engineering networks is in progress, as well as work on the arrangement of the roof. Installation of aluminum window structures is being carried out.

• On tower "G", installation of aluminum window structures of 3-25 floors and the installation of hinged ventilated facades of 3-25 floors is in progress. Bricklaying works are in progress on floors 1-24. Facade lighting work continues.

• On tower "D" assembly work of the vertical elements of the 11th floor is being carried out. Works on the construction of the stylobate are in progress.

Work on the construction of the restaurant has begun.