Dynamics of construction as of 01.11.2021
//

Dynamics of construction as of 01.11.2021

Dear customers, to your attention the dynamics of construction as of 01.11.2021.

On tower "A" works on installation of window aluminum designs (30%) proceed. Works on a bricklaying of walls (40%) are carried out. The installation of holes is completed by 80%.

On tower "B" works on installation of window aluminum designs (60%) proceed. Work on brickwork of walls (25%) continues and work on installation of hinged ventilated facades has begun.

On the tower "V" work on the roof is underway (70%). Installation of aluminum window constructions has already been completed by 60% and hinged ventilated facades - by 55%. The installation of holes is completed by 90%. Work on illumination of a facade proceeds (50%). Fortifications have been created to service the facade of the building.

On the tower “G” works on installation of hinged ventilated facades (85%) and window aluminum constructions (90%) are being completed. Work continues on the lighting of the facade (80%) and the installation of fortifications to service the facade of the building.

On the tower "D" the installation works of the vertical elements of the 17th floor continue. Work on the construction of a stylobate continues.