Переверніть Ваш пристрій
в горизонтальне положення
Look

This site uses cookies and technical data collection services. To ensure uptime and improve the quality of service. By continuing to use our site, you automatically agree to the insertion of data

Dynamics of construction as of 01.01.2022
//

Dynamics of construction as of 01.01.2022

Dear customers, for your attention the dynamics of construction as of 01.01.2022.

At tower "A", work continues on the brickwork of walls on floors 2-21, 50% of the work has already been completed. Also, work is underway on the installation of aluminum window structures 2-9 floors and 12-14 floors. Hole arrangement is 90% complete.

The roofing of tower "B" is 56% complete. Work continues on masonry walls and installation of hinged ventilated facades (35%).

Roofing works are in progress at tower "V" (75%). The installation of aluminum window structures has already been completed by 85% and hinged ventilated facades - by 68%. Work on facade lighting continues (50%). The installation of fortifications to service the building's façade is almost complete. Air conditioning and ventilation systems are installed on floors 2-6. Also, work on the installation of a smoke protection system is nearing completion.

At tower "G", work is being completed on the installation of hinged ventilated facades (85%) and aluminum window structures on floors 1-25. Facade illumination work continues, more than 80% of the work has already been completed.

On tower "D", the installation work of the vertical elements of the 17th floor has been completed. Work has begun on the laying of engineering networks.

Follow the news on how your house is built!

Subscribe to news
subscribe
subscribe
Thank you for your application!