Dear customers, we present to your attention the dynamics of construction as of 01.07.
• On tower "A" the construction of the building frame has been completed. Brickwork of the walls of 6-7 floors is under progress. Work on the installation of aluminum window structures of 3-9 floors has begun.
• On tower "B", the construction of the building frame has been completed. Brickwork of the interior walls is under progress.
• At tower "V", work continues on the arrangement of internal engineering networks, as well as work on the arrangement of the roof.
• At tower "G", work continues on the installation of aluminum window structures of 3-25 floors and the installation of hinged ventilated facades of 3-25 floors. Bricklaying works are in progress on floors 1-21. Facade lighting works are in progress.
• On tower "D" assembly work of vertical elements of the 10th floor is being carried out. Works on the construction of the stylobate are in progress.