Dynamics of construction as of 2021/05/01
05/05/21

Dynamics of construction as of 2021/05/01

Dear Customers! We present to your attention a monthly report on the construction progress of the premium multifunctional complex INTERGAL CITY.

  • On "A" tower assembly work is performed on the vertical elements of the upper technical floors.
  • Installation work of vertical elements on "B" tower has been completed. Proceeded to the brickwork of the walls.
  • On "V" tower work is in progress on the installation of internal engineering networks, as well as work on the construction of the roof.
  • At tower "G" working process on the installation of aluminum window structures of 4-16 floors and the installation of hinged ventilated facades of 8-16 floors is undergoing. Bricklaying works are in progress on floors 1-18. Facade lighting work continues. The installation of dividing walls has begun.
  • On tower "D" assembly work of the vertical elements of the 5th floor is being carried out.
  • Works on the construction of the stylobate are in progress.