Dear Customers! We present to your attention a monthly report on the construction progress of the multifunctional complex INTERGAL CITY.
- On tower "A" assembly work of the vertical elements of the 20th floor is being carried out.
- On tower "B" assembly work of vertical elements of the 9th floor is being carried out.
- Walls and partitions have been completed on tower "V". Work is being carried out on the arrangement of internal engineering networks, as well as work on the arrangement of the roof.
- At the G tower, work continues on the installation of aluminum window structures and the installation of hinged ventilated facades of 12-16 floors. Bricklaying works are in progress on floors 11-13.
- On tower "D" assembly work of the vertical elements of the 2nd floor is being carried out.
Completed work on the construction of one air bridge. Works on the construction of the stylobate are in progress.