Dynamics of construction as of 2021/06/01
03/06/21

Dynamics of construction as of 2021/06/01

Dear Customers! We present to your attention a monthly report on the construction progress of the premium multifunctional complex INTERGAL CITY.


  • On tower "A", the installation work of the vertical elements of the upper technical floors has been completed. Work on brickwork of 3-5 storey walls is in progress. Work has begun on the installation of aluminum window structures of 6-9 floors.
  • On tower "B", the installation work of the vertical elements has been completed. Work continues on the brickwork of the inner walls.
  • On tower "V", the work on the brickwork of the inner walls has been completed. Work continues on the installation of internal engineering networks, as well as work on the installation of the roof.
  • On tower "G" work continues on the installation of aluminum window structures 3-22 floors and the installation of hinged ventilated facades of 3-16 floors. Bricklaying works are in progress on floors 1-20. Facade lighting work continues. Work has begun on the installation of brackets.
  • On tower "D" assembly work of the vertical elements of the 7th floor is being carried out. Construction of the stylobate continues.