Dynamics of construction as of 25.05.20
25/05/20

Dynamics of construction as of 25.05.20

Dear customers!

Your INTERGAL CITY premium complex is growing right before our eyes, and we are happy to fix the dynamics and introduce you to it.

On the tower "A" - the floor slab is completed on the 9th floor.

On the tower "G" - a slab of the 14th floor is reinforced. Work is underway on the construction of openings for utilities.

On the tower "B" - completed the slab of the 9th floor.

Sports complex: all monolithic carcass structures are completed; parapet is performed; walls are waterproofed and soil is backfilled.

On the tower "D" piles of the retaining wall are made, excavation is being carried out.