Dear clients! We do not stop to create your dream apartments. We offer you to get acquainted with the up-to-date dynamics of construction. The status of the works is fixed as of 04/23/20.
On tower "A" - the completed overlapping slab of the 9th floor and PPC.
The tower " G" - reinforced slab floor 12 floors.
On tower "B" – working on 9 floor’s slab.
Tower "D" works on the construction pit installation.
Sports Complex: monolithic structures of all pools are made. The walls and columns of the 4th floor are being constructed.